Crews Lay the SNRC's Influent Pump Station Steel Foundation

Posted on August 14, 2019 at 4:57 PM by Roxana Morales

Additional heavy construction equipment has been delivered to the SNRC site and crews are now laying the influent pump station's steel foundation.

Influent Pump Station

During this process, crews will strategically lay over 88,000 pounds of reinforcing steel to ensure the foundation’s concrete structure keeps its shape and is able to support the anticipated weight of the facility.

Influent Pump Station Steel Foundation

Influent Pump Station Foundation

Influent Pump Station Foundation Crews Working

Once this phase has been completed, crews will pour approximately 1.5 million pounds of concrete into the steel foundation over the course of 8-12 hours without stopping. After allowing the concrete to cure for about 4 weeks, the foundation’s 30 to 35 foot walls will be installed.